This article outlines the process for starting a stage within the pdVISION system, from selecting the well and stage number to confirming execution. Following these steps ensures the correct stage is configured before beginning the job.



1. Switch to the Stage Flow Tab:

  • Navigate to the Stage Flow Tab to begin execution.



2. Select Well and Stage:

  • In the Stage Flow Panel, select the well you want to start a stage on.

  • Use the arrows to choose the correct stage number.

  • Press Confirm Stage to proceed.
  • Well and stage selection are only available before a job has started. If a job is already in progress, it must be completed before changing the well or stage.


3. Changing the well/stage selection:

  • If you need to change the stage selection, first press the Change Stage button.
     
  • Select the well and stage from the options.



Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article